The development comprises three buildings across approximately 4.5 hectares (11.1 acres), with a total built area of 35,000 m2 (approximately 385,000 ft2). The completed first phase includes a 4,700 m2 (approximately 50,600 ft2) building and a 10,000 m2 (approximately 107,600 ft2) underground garage. The second building is scheduled for completion by the end of 2026, while the central building—described as “the heart of the district”—is expected to be finished in 2027. The project contractor is GAT of Novi Sad.
Products Used
The waterproofing package includes PENETRON ADMIX for integral concrete waterproofing, along with PENETRON, PENECRETE MORTAR, and PENETRON GROUT for sealing joints, cracks, and key construction details. PENEBAR SW, a hydrophilic waterstop, was used to secure construction joints, while MULTI PATCH provided fast, reliable surface repairs.
Related Media Releases
July 28, 2026