Description
The La Mina hydro plant is located upstream from the Colbun reservoir in the Maule province in the commune of San Clemente, 110 kilometers from Talca. With two 17 MW hydroelectric units and an average annual generation of 180 GWh, the plant adds 34 MW to the SIC network.
Products Used
PENETRON ADMIX was used to waterproof the reinforced concrete structures and optimize the durability of the concrete. Further PENETRON crystalline materials were applied to the slab and walls of the engine room and over 1 km of PENEBAR SW-45 waterstop was used to permanently seal the construction joints and prevent any penetration of water.